Rule 20:10:36:64 Meeting.

          20:10:36:64.  Metering. The interconnection customer is responsible for the cost of the purchase, installation, operation, maintenance, testing, repair, and replacement of any special metering and data acquisition equipment considered necessary by the terms of the power purchase agreement. The public utility shall install, maintain, and operate the metering equipment. Parties shall be granted unrestricted access to the equipment as may be necessary for the purposes of conducting routine business.

 

          Source: 35 SDR 305, effective July 1, 2009.

          General Authority: SDCL 49-34A-27, 49-34A-93.

          Law Implemented: SDCL 49-34A-27, 49-34A-93.

 